How to configure budget settings (NetSuite)

Organisation Administrators can set a check period and how zero-planned amounts are handled for each budget.

  • On the Budget Checking page, find the budget you want to configure. Click the three-dot icon in the corner of the budget card and select Budget settings.

  • This opens the Settings pop-up, where you can set the following.

Budget check period

Choose how far the budget spans and how it's compared against requests:

  • 1 month — the budget for a request is checked against the calendar month in which the request was created.

  • Financial quarter — a three-month period that includes the month of creation, counted from the start of the financial year.

  • Half of financial year — a six-month period counted from the start of the financial year.

  • Financial year — a 12-month period counted from the start of the financial year.

  • Year to date — a rolling budget from the start of the financial year up to the month of creation.

  • Year with selected start month — a 12-month period starting from a month you choose.

  • Year to date starting from the selected month — a rolling budget from a month you choose up to the current month.

Handling a 0 planned amount

Choose how ApprovalMax treats a budget line with a planned amount of 0:

  • Ignore 0 amount and do not display the budget — the budget is left off the request entirely when its planned amount is 0.

  • Display the budget with 0 amount — the budget still appears on the request, showing 0 as the planned amount, so you can see that spending against it hasn't been budgeted for.

  • Once you've made your selections, click Save to apply them.